				| This memo is shared by city engineer Keith Lovan with members of the BPAC. 
 Just thought some folks would be interested in this.
 
 
 Bicycle Pedestrian Advisory Committee
 Project Status Report - Fayette County
 August 6, 2010
 
 New changes are noted in italics
 
 TRAIL PROJECTS
 
 Arboretum Trail (Trail Bond)
 Scope: within the Arboretum.
 Facility: Shared use trail through Walnut Woods, 700 feet
 Status: UK looking at access through Central Baptist Parking lot. Sharrows were placed on University Court. No change
 
 Armstrong Mill Connectors (part of Gainesway-CMAQ)
 Scope:  Located on the south side near Armstrong Mill and Gainesway Park.
 Facility: Shared use path; 1,600 feet, connects 6 stub streets to Gainesway Trail.
 Status: Future phase; need neighborhood meetings.  No change
 
 Beaumont Trail (unfunded)
 Scope:  Located on the south side of Lexington, connects YMCA to Beaumont HOA area.
 Facility: Shared use path; 3,000 feet.
 Status: On hold. No change
 
 Brighton East Rail Trail (SLX)
 Scope:  Located on the east side of Lexington between Bryant Road and Deer Haven Lane.
 Facility: Shared use path; primary greenway trail, two phases; each phase approx 1 mile. Part of East West Trail and Lexington Big Sandy Rail Trail.
 Status: Phase 2-Construction scheduled for Summer 2010. No change
 
 Brighton Rail Trail Phase 4 (Brighton West Rail Trail) (Trail Bond)
 Scope:  Located on the east side of Lexington between Man O’War Boulevard and Liberty Road.
 Facility: Shared use path; primary greenway trail, 2,500 feet. Connects to Brighton Rail Trail Overpass and Liberty Trail.
 Status: This section is not funded. Project put on hold. No change
 
 Brighton Rail Trail Overpass (CMAQ)
 Scope: connects Brighton East Rail Trail with Brighton Rail Trail Phase 4
 Facility: Bridge overpass, 150 feet
 Status: Notice to Proceed given to Contractor. No change
 
 Cardinal Run Park North (Trail Bond)
 Scope:  Located on the west side in Cardinal Run Park.
 Facility: Shared use path; 9,000 feet, loop trail
 Status: Plans are complete and Parks is reviewing. No change
 
 Chilesburg Trail (Trail Bond)
 Scope: Athens Boonsboro to Hayes Blvd
 Facility: Shared use path (conversion from old roadway); tertiary greenway trial
 Status:  Waiting on the developer’s contractor to begin work. Developer wants to keep the Athens Boonesboro end open for access. This will delay construction of the Hayes Blvd end. Spoke with developer and they still need access. No change.
 
 Coolavin Rail Trail (Recreational Trail Grant)
 Scope: 4th Street to active rail line at Bellaire Ave.
 Facility: Rail Trail, part of Legacy Trail.
 Status:  CSX attorney conducting title search. Received agreement. Needs signature by Mayor and Cabinet. No change
 
 Gainesway Trail (CMAQ)
 Scope:  From Tates Creek Schools to Mill Creek Elementary.
 Facility: Shared use path, approximately 2 miles.
 Status:  Parks preparing RFQ. No change
 
 HealthWays: Lafayette and Shillito Trail System (TE and Trail Bond)
 Scope: Off road trail in the Wellington Subdivision
 Facility: Shared use paths; connections to neighborhood and schools
 Status:  Construction 95% complete on Lafayette and 80% on Shillito.
 
 Highlands Park Trail (Trail Bond)
 Scope: Within Highland Park
 Facility: Shared use path in park, 2,000 feet, loop trail
 Status: Designed by Parks. On Hold. No change
 
 IMMAG Legacy Trail Head
 Scope: Trail Head infrastructure
 Facility: Legacy Trail head at intersection of 3rd Street and Midland Ave.
 Status: Design 95% complete. No change
 
 Lakeside Trail (Jacobson) (Trail Bond)
 Scope:  Located near Jacobson Park.
 Facility: Shared use path; 7,700 feet connects neighborhood to park.
 Status: Plans are complete and Parks is reviewing. No change
 
 Legacy Trail Phase 1 (TE, CMAQ, Stimulus, and Trail Bond)
 Scope:  Ironworks to Newtown Pike at Citation Blvd
 Facility: Shared use path; 6.4 miles. Includes Maine Chance Trail, Coldstream
 Status:  Construction 80% complete.  All of the bridges are set and rock is down
 
 Legacy Trail Phase 2 (Stimulus and Trail Bond)
 Scope:  Newtown Pike at Citation Blvd to Northside YMCA
 Facility: Shared use path; 2.1 miles. Includes LexMark
 Status:  Construction 90% complete.
 
 Legacy Trail Phase 3 (TE and Trail Bond)
 Scope:  Northside YMCA to Downtown
 Facility: Shared use path; 4-5 miles. Includes Downtown Segments
 Status:  Waiting on agreements. No change.
 
 Legacy Trail Enhancements (TCSP)
 Scope:  Legacy Trail enhancement and amenities
 Facility: Trail head improvement, markers and amenities.
 Status:  Waiting on agreement. No change
 
 Legacy Trail-KY Horse Park Trail (Trail Bond)
 Scope:  North Legacy Trailhead to KY Horse Park
 Facility: Shared use path; .2 miles. Connects Legacy Trail to KY Horse Park
 Status:  Construction 50% complete.
 
 Masterson Station Park Trail (Trail Bond)
 Scope:  Located on the west side of Lexington in Masterson Station Park.
 Facility: Shared use path; 10,400 feet along perimeter of park.
 Status: Waiting on documents for main trail design; design of new horse crossing (so trail can use existing) is underway. No change
 
 Masterson Station Park Trail Phase 2 (Trail Bond)
 Scope:  Located on the west side of Lexington connects to Masterson Station Park.
 Facility: Shared use path; 5,000 feet, runs through neighborhood.
 Status: Waiting on documents for main trail design; design of new horse crossing (so trail can use existing) is underway No change
 
 Meadowbrook Park Trail (Trail Bond)
 Scope: Within Meadowbrook Park
 Facility: Shared use path in park, 1,200 feet, loop trail
 Status: Parks designing project. On hold. No change.
 
 Richmond Road Trail (SLX and private funds)
 Scope: From Eagle Creek Drive to Jacobson Park
 Facility: Shared use path; primary greenway trail, approximately 1 mile
 Status:  Working on right-of-way acquisition on Phase 1B. Construction Unit Price Contract approved. Working with Contractor to construct Phase 1A. No change
 
 RJ Corman Rail with Trail (Trail Bond)
 Scope: Feasibility Study of rail with trail from downtown to Woodford County line.
 Facility: Shared use path; rail with trail; approximately 1 mile
 Status:  RJ Corman is interested in rail with trail. Negotiating r/w trade. No change
 
 South Elkhorn Trail Section 2 (TE and SLX)
 Scope: From Joseph Bryan Way to Waveland State Historic Site.
 Facility: Shared use path; primary greenway trail, 1,700 feet
 Status: Received confirmation from Law that an agreement from Norfolk Southern is not needed for tunnel. The next step is obtaining an easement from UK. Description has been sent to UK for their review. No change
 
 South Elkhorn Trail Section 3 (TE and SLX)
 Scope: From Lochdale Terrace to Shillito Park
 Facility: Shared use path; primary greenway trail, 1,700 feet
 Status:  Consultant has started design. Consultant submitted plans to Norfolk Southern. Mayor sent letter to Norfolk Southern requesting permission for a rail with trail. No change
 
 South Elkhorn Highlands Trail (Trail Bond)
 Scope:  Located on the south side of Lexington, connects Southpoint Park to Veterans Park.
 Facility: Shared use path; 5,200 feet.
 Status: On hold. No change
 
 South Elkhorn Waveland Trail (Trail Bond)
 Scope:  Located on the south side of Lexington, connects South Elkhorn Trail to Mill Pond. Part of Waveland Museum Lane
 Facility: Shared use path; 4,500 feet.
 Status: Waiting on road closure. No change
 
 Southpointe Park Trail Phase 2 (Trail Bond)
 Scope: connects loop trail in Southpointe Park to South Elkhorn Trail.
 Facility: Shared use path in park, 1,200 feet
 Status: on hold. No change.
 
 Town Branch Trail Phase 3 (TE)
 Scope: From McConnell Springs to Old Frankfort Landfill.
 Facility: Shared use path; primary greenway trail, approximately 1 mile. Part of East West Trail.
 Status:  Working on feasibility study before starting design. No change
 
 Town Branch Trail Phase 4 (Trail Bond)
 Scope: From Alexandria Drive to New Circle Road.
 Facility: Shared use path; primary greenway trail, approximately 13, 000 feet. Part of East West Trail.
 Status:  Consultant started feasibility study. No change.
 
 Town Branch Trail Lexington Distillery District (local bond)
 Scope: From Forbes Road to Newtown Pike Extension.
 Facility: Shared use path; primary greenway trail, approximately 1 mile. Part of East West Trail.
 Status: Project on hold No change
 
 Town Branch Connector Trail (Trail Bond and Water Quality Management Fee)
 Scope:  Located on the west side of Lexington in McConnells Trace Subdivision.
 Facility: Shared use path; connects to Town Branch Trail. 2,300 feet.
 Status: Need to correct drainage problems before proceeding. Consultant has started design. No change
 
 Town Branch Trail Crossing (CMAQ)
 Scope:  Improve sight distance on Old Frankfort Pike for Town Branch Trail
 Facility:  Mid block crossing.
 Status:  Funding announced in September 2009.  No change
 
 Valley Park Trail Phase 2 (Trail Bond)
 Scope: Within Valley Park
 Facility: Shared use path in park, 1,700 feet, loop trail
 Status: Parks designing trail. No change
 
 Veterans Park Trail Phase 1 (Trail Bond)
 Scope:  Located on the south side of Lexington in Veterans Park.
 Facility: Shared use path; 5,600 primary greenway trail, part of North South Trail.
 Status: Parks designing project. On hold. No change
 
 Veterans Park Trail Phase 2 (Trail Bond)
 Scope:  Located on the south side of Lexington in Veterans Park.
 Facility: Shared use path; 3,000 mountain bike trail.
 Status: Plans are complete and Parks is reviewing. No change
 
 West Hickman Trail (SLX)
 Scope: From Man O’ War at Clearwater Way to Veterans Park.
 Facility: Shared use path; primary greenway trail, approximately 7,000 feet
 Status: Construction 95% complete.
 
 ROAD PROJECTS
 
 Citation Boulevard (SP)
 Scope:  From intersection of Alexandria and Leestown to Georgetown Road
 Facility:  Road improvement project that includes bike lanes and sidewalks
 Status:   In design, Construction slated to start in 2010. No change
 
 Chevy Chase Intersection (Corridors Commission, construction unfunded)
 Scope:  Study to determine construction costs.
 Facility:  Streetscape project for High/Euclid/Fontaine/Tates Creek intersection to improved bike and pedestrian facilities
 Status:  Consultant conducting public meetings
 
 Clay Mill Road Section 1 (SLX)
 Scope:  Harrodsburg Rd to New Circle Rd
 Facility: Road improvement project that includes bike lanes and sidewalks
 Status:  Design underway. No Change
 
 Clay Mill Road Section 2A (SLX)
 Scope:  Higbee Mill Rd to Keithshire Way.
 Facility: Road improvement project that includes bike lanes and sidewalks
 Status:  Design complete. Right of way acquired and Utility Relocations underway. Bid in August.   No change
 
 Clay Mill Road Section 2B (SLX)
 Scope:  New Circle Rd to Keithshire Way
 Facility:  Road improvement project that includes bike lanes and sidewalks
 Status:  Design underway.  No change
 
 Clay Mill Road Section 2C (SLX)
 Scope:  Higbee Mill Road to Twain Ridge
 Facility: Road improvement project that includes bike lanes and sidewalks
 Status:  Design underway.  No change
 
 Harrodsburg Road (SP)
 Scope:  Pasadenda/Alexandria Drive to Beaumont Centre Parkway
 Facility:  Undetermined
 Status:  Preliminary Design underway. No change
 
 Leestown Road (SP Bond)
 Scope:  Greendale Rd to Masterson Station Park
 Facility: Road improvement project that includes bike lanes and sidewalks
 Status:  Project under design. Construction pushed back to 2013. No change
 
 Liberty/Todds Road – Section 1B (Stimulus, HPP and SLX)
 Scope:  MOW to Forest Hill Dr
 Facility:  Road improvement project that includes bike lanes and sidewalks
 Status: Construction 80% complete.
 
 Liberty/Todds Road - Section 2 (SLX)
 Scope:  Forest Hill Dr to Polo Club Blvd
 Facility:  Road improvement project that includes bike lanes and sidewalks
 Status: Project under design. No change
 
 Manchester Street Streetscape (local bond)
 Scope: From South Forbes to Newtown Pike Extension.
 Facility: Streetscape project to include sidewalks and bike lanes.
 Status: Project on hold.  No change
 
 Main and Vine Street  Streetscape (Stimulus)
 Scope: Main Street from Broadway to Elm Tree and Vine Street from Broadway to Limestone
 Facility: bike lanes and sidewalk improvements
 Status: Construction 80% complete.
 
 Mt. Tabor Road (Unfunded)
 Scope:  Service road to Patchen Dr.
 Facility:  Road improvement project that includes bike lanes and sidewalks
 Status:  ROW is being purchased but there is no funding for construction. No change.
 
 Newtown Pike Extension (SLX and Stimulus)
 Scope:  Main St to S Limestone St.
 Facility:  Road improvement project that includes bike lanes and sidewalks
 Status:  Construction 80% complete
 
 Newtown Pike (Unfunded)
 Scope:  New Circle Road to I 75
 Facility:  Road improvement project. Bike lanes and sidewalk on east side
 Status:  In preliminary design phase.  No change
 
 Polo Club Blvd (D SLX, C not in TIP but SLX in KYTC 6 yr plan)
 Scope:  Man O War Blvd to Todds Road, design from Deerhaven to Todds
 Facility:  Bike lane striping, design for construction
 Status: Preparing RFQ for design. No change.
 
 Rose Street (SLX)
 Scope:  Rose Lane to Euclid Ave.
 Facility:  Bike lane extension, one block
 Status:  UK and Utility companies reviewing plans. No change
 
 Rosemont Garden Improvements (unfunded)
 Scope:	railroad to Lafayette Parkway
 Facility: bike lanes and sidewalk
 Status: Design on hold. No funding for right of way or construction. No change.
 
 
 
 Sidewalk Projects
 
 Armstrong Mill Sidewalk (unfunded)
 Scope: Tates Creek to Greentree Rd
 Facility:  Sidewalk on north side of roadway
 Status:  Preliminary design complete.  No change.
 
 Maxwell St Sidewalk and Bike Lane (CMAQ)
 Scope:  From Rose Street to Woodland Ave
 Facility: Project to remove parking and add a bike lane and reconstruct curb and sidewalk
 Status:  Contractor started July 12th.
 
 Southland Drive Bike Lane and Sidewalk Project (CMAQ)
 Scope:  Nicholasville Road to Rosemont Garden
 Facility:  Bike lanes along Southland Dr and sidewalk connection at railroad underpass.
 Status:  Funding announced in September 2009.  No change
 
 Tates Creek Road Sidewalks (CMAQ)
 Scope:  Montclair/Lakewood Drive to Lansdowne Shoppes/Dove Run Road
 Facility:  Sidewalks on both sides of the street
 Status:  Consultant has started design. No change
 
 West Loudon Avenue Sidewalk Project (CMAQ)
 Scope:  Newtown Pike to Russell Cave
 Facility:  Sidewalks on both sides of the street where missing.
 Status:  Funding announced in September 2009.  No change
 |  |  
		| Back to top |  |  
		|  |  
		| sailorjames cutter
 
  
 
 Joined: 15 Nov 2007
 Posts: 329
 
 
 | 
			
				|  Posted: Fri Aug 13, 2010 7:40 am    Post subject: |   |  
				| 
 |  
				| Thank you, glad to see these kind of things made public and accessible. |  |  
		| Back to top |  |  
		|  |  
		| metro biking hipster
 
  
 
 Joined: 16 Mar 2008
 Posts: 64
 Location: Lexington, KY
 
 | 
			
				|  Posted: Sat Aug 14, 2010 8:05 am    Post subject: Project Postings |   |  
				| 
 |  
				| T - Appreciate the post RE LFUCG status reports.  Maybe we could get these posted after each monthly meeting.  I know people get frustrated at the bureaucratic pace bike/ped projects get implemented, but Keith, Kenzie and others in the MPO can only shepard through what comes available by funding.  Additional interest and support from Community walkers and riders helps convey the message upward that there is a demand which helps money to flow back down. See you all at Trailapalooza - just the kind of visible advocacy opportunity that gets attention - thanks Van, Zina, Dave, Boyd, Marty, sponsors, and everyone else.
 M
 _________________
 Metro Biking
 |  |  
		| Back to top |  |  
		|  |  
		| politicalhero cutter
 
  
 
 Joined: 22 Oct 2007
 Posts: 657
 Location: Sexy Lexi on the Southside
 
 | 
			
				|  Posted: Sun Aug 15, 2010 8:07 am    Post subject: |   |  
				| 
 |  
				| Mike, yup I will post these after every BPAC meeting.  I think it is good to let folks know where the projects are.  I know I get really irritated when it seems like a simple project yet it takes years to complete. |  |  
		| Back to top |  |  
		|  |  
		| roller d'oh!
 
  
 
 Joined: 17 May 2008
 Posts: 294
 Location: duncan park
 
 | 
			
				|  Posted: Mon Aug 16, 2010 10:39 am    Post subject: |   |  
				| 
 |  
				| Thanks for posting this list and there's a lot mileage planned. Here's another list of completed projects for comparison (from September, 2009, LFUCG) and a city map from July, 2009. Probably the most exciting in my opinion are the rail trails. 
 Completed trails:
 
 Addison:				1/3 mile paved trail off Pine Meadows Drive / Garrison Avenue
 Arboretum:			2 mile paved trail off Alumni Drive (Note: Bikes are NOT permitted.)
 Beaumont Preserve:	1 mile paved trail off Allegheny Way beside Rosa Parks Elementary School
 Belleau Woods:		1 mile paved trail to Pleasant Ridge Park
 Coldstream Park:		2 mile paved trail off McGrathiana Parkway (Newtown and I-75)
 Constitution:		3/4 mile asphalt trail off Old Paris Pike / Rookwood Drive
 Cross Keys:		1/4 mile gravel trail off Cross Keys Road
 Day Treament:		5/8 mile paved trail of Red Mile Place (connects to Addison Park)
 Dogwood Trail:	1/2 mile paved loop off of Dogwood Trace Boulevard
 Elizabeth Street:	1/2 mile sidewalk off Elizabeth Street Garden
 Garden Springs:		1/2 mile paved trail off Garden Springs Dr.
 Harrod Hill Park:	1/2 mile paved trail off Ridgecane Rd.
 Hartland Park:		1/2 mile paved trail off Kenesaw Road
 Higbee Mill Park:	1/2 mile paved trail (corner of Clays Mill Rd. and Old Higbee Mill Rd.)
 Kirklevington:		3/4 mile paved trail off Redding Road
 Lakeview:			1/2 mile paved trail off Laketower Drive
 Lansdowne-Merrick:	1 1/2 mile paved trail off Pepperhill Rd. beside Julius Marks Elementary School
 Liberty Trail:		1/2 mile paved trail off Starshoot Parkway
 Martin Luther King:	1/3 mile paved trail off McCullough Drive
 Mary Todd Park:		1/4 mile paved trail off Rodgers Road
 Masterson Station:	4 mile perimeter grass course (front to back of park)
 McConnell Springs:	1/2 mile paved trail at end of Rebmann Lane off Old Frankfort Pike
 Meadowbrook:		1/4 mile paved trail at end of Harvard Lane off of E. Tiverton
 Mount Tabor:		1/3 mile paved trail off Eureka Springs or at end of Elk Creek Drive
 Pine Meadows:		1/5 mile paved trail at end of Tazewell Drive
 Raven Run:			10+ miles trails - paved and unpaved; Freedom Trail designed for visually impaired
 Riverhill Park:		1/2 mile paved trail and sidewalk
 Shillito Park: 2 mile perimeter grass off Reynolds Road, behind Fayette Mall
 South Elkhorn:		1/2 mile asphalt trail off Newbury Way
 Southpoint Park:		1/2 mile off Graves Drive
 Squires Road:		1 1/3 mile paved trail from Summerhill Dr. to Squires Road; access at Berry Hill Park
 Stonewall Park:		1/2 mile unpaved trail off Cornwall
 Town Branch Trail:	2 mile paved trail off Long Branch Lane
 Valley Park:			1/3 mile paved trail off Cambridge Drive
 Veterans Park:		1 mile paved trail off Southpoint Drive
 Waverly:				1 kilometer paved trail off Twain Ridge Drive
 Wellington Park:		1 1/4 mile paved trail off Wellington Way
 Wellington Trail:	1 mile paved trail along Keithshire Way / Reynolds Road (Construction of second loop will be underway this summer.)
 |  |  
		| Back to top |  |  
		|  |  
		| brokebike cutter
 
  
 
 Joined: 21 Oct 2007
 Posts: 2434
 Location: local
 
 | 
			
				|  Posted: Mon Aug 16, 2010 12:50 pm    Post subject: |   |  
				| 
 |  
				| Are all the paved trails also shared use paths? Meaning, they are open to bikes and pedestrians? _________________
 ------------[]  O
 |  |  
		| Back to top |  |  
		|  |  
		| roller d'oh!
 
  
 
 Joined: 17 May 2008
 Posts: 294
 Location: duncan park
 
 | 
			
				|  Posted: Mon Aug 16, 2010 2:07 pm    Post subject: |   |  
				| 
 |  
				|  	  | brokebike wrote: |  	  | Are all the paved trails also shared use paths? Meaning, they are open to bikes and pedestrians? | 
 
 You mean the green solid lines on the map? No, in most cases I suspect. The paved walking trails in the arboretum, McConnell Springs, and Constitution park are examples. I think if you had training wheels, you could probably bike them.
 |  |  
		| Back to top |  |  
		|  |  
		|  |  
  
	| 
 
 | You cannot post new topics in this forum You cannot reply to topics in this forum
 You cannot edit your posts in this forum
 You cannot delete your posts in this forum
 You cannot vote in polls in this forum
 
 |  
 Powered by phpBB © 2001, 2005 phpBB Group
 
 |