LexRides Forum Index LexRides
Lexington's Bike Forum
 
 FAQFAQ   SearchSearch   MemberlistMemberlist   UsergroupsUsergroups   RegisterRegister 
 ProfileProfile   Log in to check your private messagesLog in to check your private messages   Log inLog in 

September Update on Bike/Ped Projects

 
Post new topic   Reply to topic    LexRides Forum Index -> Local Bike Advocacy
View previous topic :: View next topic  
Author Message
politicalhero
cutter
cutter


Joined: 22 Oct 2007
Posts: 657
Location: Sexy Lexi on the Southside

PostPosted: Thu Sep 09, 2010 2:33 pm    Post subject: September Update on Bike/Ped Projects Reply with quote

Bicycle Pedestrian Advisory Committee
Project Status Report - Fayette County
September 10, 2010

New changes are noted in italics

TRAIL PROJECTS

Arboretum Trail (Trail Bond)
Scope: within the Arboretum.
Facility: Shared use trail through Walnut Woods, 700 feet
Status: UK looking at access through Central Baptist Parking lot. Sharrows were placed on University Court. No change

Armstrong Mill Connectors (part of Gainesway-CMAQ)
Scope: Located on the south side near Armstrong Mill and Gainesway Park.
Facility: Shared use path; 1,600 feet, connects 6 stub streets to Gainesway Trail.
Status: Future phase; need neighborhood meetings. No change

Beaumont Trail (unfunded)
Scope: Located on the south side of Lexington, connects YMCA to Beaumont HOA area.
Facility: Shared use path; 3,000 feet.
Status: On hold. No change

Brighton East Rail Trail (SLX)
Scope: Located on the east side of Lexington between Bryant Road and Deer Haven Lane.
Facility: Shared use path; primary greenway trail, two phases; each phase approx 1 mile. Part of East West Trail and Lexington Big Sandy Rail Trail.
Status: Phase 2-Construction scheduled for 2011.

Brighton Rail Trail Phase 4 (Brighton West Rail Trail) (Trail Bond)
Scope: Located on the east side of Lexington between Man O’War Boulevard and Liberty Road.
Facility: Shared use path; primary greenway trail, 2,500 feet. Connects to Brighton Rail Trail Overpass and Liberty Trail.
Status: This section is not funded. Project put on hold. No change

Brighton Rail Trail Overpass (CMAQ)
Scope: connects Brighton East Rail Trail with Brighton Rail Trail Phase 4
Facility: Bridge overpass, 150 feet
Status: Design has started.

Cardinal Run Park North (Trail Bond)
Scope: Located on the west side in Cardinal Run Park.
Facility: Shared use path; 9,000 feet, loop trail
Status: Plans are complete and Parks is reviewing. No change

Chilesburg Trail (Trail Bond)
Scope: Athens Boonsboro to Hayes Blvd
Facility: Shared use path (conversion from old roadway); tertiary greenway trial
Status: Waiting on the developer’s contractor to begin work. Developer wants to keep the Athens Boonesboro end open for access. This will delay construction of the Hayes Blvd end. Spoke with developer and they still need access. No change.

Coolavin Rail Trail (Recreational Trail Grant)
Scope: 4th Street to active rail line at Bellaire Ave.
Facility: Rail Trail, part of Legacy Trail.
Status: CSX attorney conducting title search. Received agreement. Needs signature by Mayor and Cabinet. No change

Gainesway Trail (CMAQ)
Scope: From Tates Creek Schools to Mill Creek Elementary.
Facility: Shared use path, approximately 2 miles.
Status: Parks preparing RFQ. No change

HealthWays: Lafayette and Shillito Trail System (TE and Trail Bond)
Scope: Off road trail in the Wellington Subdivision
Facility: Shared use paths; connections to neighborhood and schools
Status: Construction complete. Trails are open.

Highlands Park Trail (Trail Bond)
Scope: Within Highland Park
Facility: Shared use path in park, 2,000 feet, loop trail
Status: Designed by Parks. On Hold. No change

IMMAG Legacy Trail Head
Scope: Trail Head infrastructure
Facility: Legacy Trail head at intersection of 3rd Street and Midland Ave.
Status: Design 95% complete. No change

Lakeside Trail (Jacobson) (Trail Bond)
Scope: Located near Jacobson Park.
Facility: Shared use path; 7,700 feet connects neighborhood to park.
Status: Plans are complete and Parks is reviewing. No change

Legacy Trail Phase 1 (TE, CMAQ, Stimulus, and Trail Bond)
Scope: Ironworks to Newtown Pike at Citation Blvd
Facility: Shared use path; 6.4 miles. Includes Maine Chance Trail, Coldstream
Status: Construction 95% complete. Grand Opening is Sept 12th

Legacy Trail Phase 2 (Stimulus and Trail Bond)
Scope: Newtown Pike at Citation Blvd to Northside YMCA
Facility: Shared use path; 2.1 miles. Includes LexMark
Status: Construction 95% complete. Grand Opening is Sept 12th.

Legacy Trail Phase 3 (TE and Trail Bond)
Scope: Northside YMCA to Downtown
Facility: Shared use path; 4-5 miles. Includes Downtown Segments
Status: Waiting on agreements. No change.

Legacy Trail Enhancements (TCSP)
Scope: Legacy Trail enhancement and amenities
Facility: Trail head improvement, markers and amenities.
Status: Waiting on agreement. No change

Legacy Trail-KY Horse Park Trail (Trail Bond)
Scope: North Legacy Trailhead to KY Horse Park
Facility: Shared use path; .2 miles. Connects Legacy Trail to KY Horse Park
Status: Construction 95% complete. Grand Opening is Sept 12th

Masterson Station Park Trail (Trail Bond)
Scope: Located on the west side of Lexington in Masterson Station Park.
Facility: Shared use path; 10,400 feet along perimeter of park.
Status: Waiting on documents for main trail design; design of new horse crossing (so trail can use existing) is underway. No change

Masterson Station Park Trail Phase 2 (Trail Bond)
Scope: Located on the west side of Lexington connects to Masterson Station Park.
Facility: Shared use path; 5,000 feet, runs through neighborhood.
Status: Waiting on documents for main trail design; design of new horse crossing (so trail can use existing) is underway No change

Meadowbrook Park Trail (Trail Bond)
Scope: Within Meadowbrook Park
Facility: Shared use path in park, 1,200 feet, loop trail
Status: Parks designing project. On hold. No change.

Richmond Road Trail (SLX and private funds)
Scope: From Eagle Creek Drive to Jacobson Park
Facility: Shared use path; primary greenway trail, approximately 1 mile
Status: Working on right-of-way acquisition on Phase 1B. Construction Unit Price Contract approved. Working with Contractor to construct Phase 1A. No change

RJ Corman Rail with Trail (Trail Bond)
Scope: Feasibility Study of rail with trail from downtown to Woodford County line.
Facility: Shared use path; rail with trail; approximately 1 mile
Status: RJ Corman is interested in rail with trail. Negotiating r/w trade. No change

South Elkhorn Trail Section 2 (TE and SLX)
Scope: From Joseph Bryan Way to Waveland State Historic Site.
Facility: Shared use path; primary greenway trail, 1,700 feet
Status: Received confirmation from Law that an agreement from Norfolk Southern is not needed for tunnel. The next step is obtaining an easement from UK. Description has been sent to UK for their review. No change

South Elkhorn Trail Section 3 (TE and SLX)
Scope: From Lochdale Terrace to Shillito Park
Facility: Shared use path; primary greenway trail, 1,700 feet
Status: Consultant has started design. Consultant submitted plans to Norfolk Southern. Mayor sent letter to Norfolk Southern requesting permission for a rail with trail. No change

South Elkhorn Highlands Trail (Trail Bond)
Scope: Located on the south side of Lexington, connects Southpoint Park to Veterans Park.
Facility: Shared use path; 5,200 feet.
Status: On hold. No change

South Elkhorn Waveland Trail (Trail Bond)
Scope: Located on the south side of Lexington, connects South Elkhorn Trail to Mill Pond. Part of Waveland Museum Lane
Facility: Shared use path; 4,500 feet.
Status: Waiting on road closure. No change

Southpointe Park Trail Phase 2 (Trail Bond)
Scope: connects loop trail in Southpointe Park to South Elkhorn Trail.
Facility: Shared use path in park, 1,200 feet
Status: on hold. No change.

Town Branch Trail Phase 3 (TE)
Scope: From McConnell Springs to Old Frankfort Landfill.
Facility: Shared use path; primary greenway trail, approximately 1 mile. Part of East West Trail.
Status: Working on feasibility study before starting design. No change

Town Branch Trail Phase 4 (Trail Bond)
Scope: From Alexandria Drive to New Circle Road.
Facility: Shared use path; primary greenway trail, approximately 13, 000 feet. Part of East West Trail.
Status: Consultant started feasibility study. No change.

Town Branch Trail Lexington Distillery District (local bond)
Scope: From Forbes Road to Newtown Pike Extension.
Facility: Shared use path; primary greenway trail, approximately 1 mile. Part of East West Trail.
Status: Project on hold No change

Town Branch Connector Trail (Trail Bond and Water Quality Management Fee)
Scope: Located on the west side of Lexington in McConnells Trace Subdivision.
Facility: Shared use path; connects to Town Branch Trail. 2,300 feet.
Status: Need to correct drainage problems before proceeding. Consultant has started design. No change

Town Branch Trail Crossing (CMAQ)
Scope: Improve sight distance on Old Frankfort Pike for Town Branch Trail
Facility: Mid block crossing.
Status: Funding announced in September 2009. No change

Valley Park Trail Phase 2 (Trail Bond)
Scope: Within Valley Park
Facility: Shared use path in park, 1,700 feet, loop trail
Status: Parks designing trail. No change

Veterans Park Trail Phase 1 (Trail Bond)
Scope: Located on the south side of Lexington in Veterans Park.
Facility: Shared use path; 5,600 primary greenway trail, part of North South Trail.
Status: Parks designing project. On hold. No change

Veterans Park Trail Phase 2 (Trail Bond)
Scope: Located on the south side of Lexington in Veterans Park.
Facility: Shared use path; 3,000 mountain bike trail.
Status: Plans are complete and Parks is reviewing. No change

West Hickman Trail (SLX)
Scope: From Man O’ War at Clearwater Way to Veterans Park.
Facility: Shared use path; primary greenway trail, approximately 7,000 feet
Status: Construction 96% complete.

ROAD PROJECTS

Citation Boulevard (SP)
Scope: From intersection of Alexandria and Leestown to Georgetown Road
Facility: Road improvement project that includes bike lanes and sidewalks
Status: In design, Construction slated to start in 2010. No change

Chevy Chase Intersection (Corridors Commission, construction unfunded)
Scope: Study to determine construction costs.
Facility: Streetscape project for High/Euclid/Fontaine/Tates Creek intersection to improved bike and pedestrian facilities
Status: Consultant conducting public meetings

Clay Mill Road Section 1 (SLX)
Scope: Harrodsburg Rd to New Circle Rd
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Design underway. No Change

Clay Mill Road Section 2A (SLX)
Scope: Higbee Mill Rd to Keithshire Way.
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Design complete. Right of way acquired and Utility Relocations underway. Bid in October.

Clay Mill Road Section 2B (SLX)
Scope: New Circle Rd to Keithshire Way
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Design underway. No change

Clay Mill Road Section 2C (SLX)
Scope: Higbee Mill Road to Twain Ridge
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Design underway. No change

Harrodsburg Road (SP)
Scope: Pasadenda/Alexandria Drive to Beaumont Centre Parkway
Facility: Diverging Diamond –speed limit reduced to 25 mph and wide curb lanes. Sidewalk on north side.
Status: Preliminary Design underway. No change

Leestown Road (SP Bond)
Scope: Greendale Rd to Masterson Station Park
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Project under design. Construction pushed back to 2013. No change

Liberty/Todds Road – Section 1B (Stimulus, HPP and SLX)
Scope: MOW to Forest Hill Dr
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Construction 90% complete.

Liberty/Todds Road - Section 2 (SLX)
Scope: Forest Hill Dr to Polo Club Blvd
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Project under design. No change

Manchester Street Streetscape (local bond)
Scope: From South Forbes to Newtown Pike Extension.
Facility: Streetscape project to include sidewalks and bike lanes.
Status: Project on hold. No change

Main and Vine Street Streetscape (Stimulus)
Scope: Main Street from Broadway to Elm Tree and Vine Street from Broadway to Limestone
Facility: bike lanes and sidewalk improvements
Status: Construction 95% complete. Grand Opening Sept 10th

Mt. Tabor Road (Unfunded)
Scope: Service road to Patchen Dr.
Facility: Road improvement project that includes bike lanes and sidewalks
Status: ROW is being purchased but there is no funding for construction. No change.

Newtown Pike Extension (SLX and Stimulus)
Scope: Main St to S Limestone St.
Facility: Road improvement project that includes bike lanes and sidewalks
Status: Construction 95% complete. Grand Opening Sept 8th

Newtown Pike (Unfunded)
Scope: New Circle Road to I 75
Facility: Road improvement project. Bike lanes and sidewalk on east side
Status: In preliminary design phase. No change

Polo Club Blvd (D SLX, C not in TIP but SLX in KYTC 6 yr plan)
Scope: Man O War Blvd to Todds Road, design from Deerhaven to Todds
Facility: Bike lane striping, design for construction
Status: Preparing RFQ for design. No change.

Rose Street (SLX)
Scope: Rose Lane to Euclid Ave.
Facility: Bike lane extension, one block
Status: UK and Utility companies reviewing plans. No change

Rosemont Garden Improvements (unfunded)
Scope: railroad to Lafayette Parkway
Facility: bike lanes and sidewalk
Status: Design on hold. No funding for right of way or construction. No change.



Sidewalk Projects

Armstrong Mill Sidewalk (unfunded)
Scope: Tates Creek to Greentree Rd
Facility: Sidewalk on north side of roadway
Status: Preliminary design complete. No change.

Maxwell St Sidewalk and Bike Lane (CMAQ)
Scope: From Rose Street to Woodland Ave
Facility: Project to remove parking and add a bike lane and reconstruct curb and sidewalk
Status: Contractor started July 12th.

Southland Drive Bike Lane and Sidewalk Project (CMAQ)
Scope: Nicholasville Road to Rosemont Garden
Facility: Bike lanes along Southland Dr and sidewalk connection at railroad underpass.
Status: Funding announced in September 2009. No change

Tates Creek Road Sidewalks (CMAQ)
Scope: Montclair/Lakewood Drive to Lansdowne Shoppes/Dove Run Road
Facility: Sidewalks on both sides of the street
Status: Consultant has started design. No change

West Loudon Avenue Sidewalk Project (CMAQ)
Scope: Newtown Pike to Russell Cave
Facility: Sidewalks on both sides of the street where missing.
Status: Funding announced in September 2009. No change
Back to top
View user's profile Send private message Visit poster's website AIM Address
Display posts from previous:   
Post new topic   Reply to topic    LexRides Forum Index -> Local Bike Advocacy All times are GMT - 6 Hours
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum


Powered by phpBB © 2001, 2005 phpBB Group